top of page

How long will it take to complete a full bespoke home automation project?

Writer's picture: SOV PropertySOV Property

Updated: Nov 4, 2024

Completing a full bespoke home automation project for a 5,000 square foot home typically takes 8 to 12 weeks. Here’s a breakdown of the process:


  • Planning and Design (1-2 weeks): Initial consultations and system design.

  • Pre-wiring and Infrastructure Setup (2-3 weeks): Installing wiring for circuits and devices.

  • Installation of Equipment (2-3 weeks): Mounting hardware and installing systems.

  • Control System Setup and Programming (2-4 weeks): Centralised control setup and device integration.

  • Testing and Handover (1 week): Final testing and homeowner training.


Note that the timeline can vary based on project complexity, material availability, and client changes.

Bespoke home automation


3 views0 comments

Recent Posts

See All

Comments


bottom of page