Let's give you an example. Completing a full bespoke home automation project for a 5,000 square foot home typically takes 8 to 12 weeks, including planning, installation, programming, and testing.
Planning and Design (1-2 weeks): Initial consultations, system design, and coordination with other contractors.
Pre-wiring and Infrastructure Setup (2-3 weeks): Installing wiring for circuits, speakers, cameras, alarms, and other infrastructure.
Installation of Equipment (2-3 weeks): Mounting hardware and installing lighting, alarm, and climate control systems.
Control System Setup and Programming (2-4 weeks): Setting up the centralised control system, integrating devices, and fine-tuning.
Testing and Handover (1 week): Testing, homeowner training, and final adjustments.
The timeline can vary based on project complexity, material delays, contractor coordination, or client changes.